First Article Inspection Skill

Purpose

The First Article Inspection skill provides capabilities for planning and executing first article inspections per AS9102, enabling comprehensive verification of manufacturing processes and design conformance.

Capabilities

  • FAI plan development per AS9102
  • Balloon drawing preparation
  • Measurement method specification
  • CMM programming guidance
  • Characteristic accountability matrix
  • Partial FAI and delta FAI management
  • FAI report generation (Forms 1, 2, 3)
  • Non-conformance disposition

Usage Guidelines

AS9102 Requirements

FAI Triggers

Full FAI required when:
- New part number
- Design change affecting form/fit/function
- Change in manufacturing process/location
- Tooling inactive > 2 years
- Manufacturing process change
- Natural/human-made event affecting process

Partial FAI (Delta FAI)

Allowed when:
- Minor design change
- Controlled process change
- Tooling modification

Only affected characteristics need re-inspection

FAI Planning

Characteristic Identification

  1. Drawing Review

    • Identify all dimensions
    • Identify all notes
    • Identify material/process requirements
    • Identify special characteristics
  2. Characteristic Types

    TypeSymbolDefinition
    StandardNoneNormal inspection
    CriticalTriangle/diamondSafety/function critical
    MajorM in circleImportant for assembly
    CTQKey symbolCustomer specified

Balloon Drawing

Ballooning requirements:
- Unique number for each characteristic
- Sequential numbering preferred
- Reference to original dimension
- Include notes and specifications
- Mark special characteristics

AS9102 Forms

Form 1: Part Number Accountability

Required fields:
- Part number and name
- Part revision level
- Drawing number and revision
- Organization name and code
- FAI report number
- Signature and date
- Part serial number
- FAI reason (new/change)

Form 2: Product Accountability - Materials, Processes, Functional Testing

Material verification:
- Material specification
- Raw material supplier
- Material certifications
- Heat/lot traceability

Process verification:
- Special processes (heat treat, plating, NDT)
- Process specification
- Processor certification
- Process parameters

Functional testing:
- Test requirements
- Test results
- Pass/fail status

Form 3: Characteristic Accountability

For each characteristic:
- Characteristic number (balloon)
- Reference location (drawing zone)
- Characteristic designator (if special)
- Requirement (nominal and tolerance)
- Results (actual value)
- Designed tooling (Y/N)
- Non-conformance number (if applicable)

Measurement Methods

Measurement Selection

ToleranceAccuracy RequiredTypical Method
+/- 0.5 mm0.05 mmCaliper
+/- 0.1 mm0.01 mmMicrometer
+/- 0.025 mm0.002 mmCMM
+/- 0.005 mm0.0005 mmPrecision CMM

GD&T Measurement

CharacteristicMeasurement Method
FlatnessCMM scan, optical flat
PerpendicularityCMM, square fixture
PositionCMM, functional gage
ConcentricityCMM, roundness tester
RunoutV-blocks + indicator
ProfileCMM, optical comparator

CMM Programming

CMM measurement strategy:
1. Establish datum reference frame
2. Measure datum features first
3. Measure located features
4. Use appropriate probe compensation
5. Verify measurement uncertainty
6. Document probe configuration

Non-Conformance Handling

Disposition Options

DispositionApplicationAuthority
Use As-IsMinor deviation, no impactEngineering
ReworkCan be brought to specQuality
RepairAlternate method to restoreEngineering
ScrapCannot be made conformingQuality
Return to SupplierVendor issuePurchasing

Documentation Requirements

Non-conformance record:
- NC number
- Characteristic affected
- Requirement
- Actual condition
- Root cause analysis
- Corrective action
- Disposition and approval

FAI Approval Process

Approval workflow:
1. Inspector completes inspection
2. Quality review forms
3. Engineering review (if NC exists)
4. Quality approval signature
5. Customer approval (if required)
6. Archive and distribution

Process Integration

  • ME-023: First Article Inspection (FAI)

Input Schema

{
  "part_info": {
    "part_number": "string",
    "revision": "string",
    "description": "string",
    "drawing_number": "string"
  },
  "fai_type": "full|partial|delta",
  "trigger": "new_part|design_change|process_change|other",
  "previous_fai": "string (if partial/delta)",
  "special_requirements": {
    "customer_approval": "boolean",
    "special_processes": "array"
  }
}

Output Schema

{
  "fai_plan": {
    "fai_number": "string",
    "balloon_drawing": "file reference",
    "characteristic_count": "number",
    "measurement_methods": "array"
  },
  "fai_forms": {
    "form_1": "document reference",
    "form_2": "document reference",
    "form_3": "document reference"
  },
  "results_summary": {
    "total_characteristics": "number",
    "conforming": "number",
    "non_conforming": "number",
    "nc_numbers": "array"
  },
  "approval_status": {
    "status": "approved|conditional|rejected",
    "conditions": "array (if conditional)",
    "approved_by": "string",
    "date": "date"
  }
}

Best Practices

  1. Review drawing completely before ballooning
  2. Ensure measurement method capability
  3. Document traceability to raw material
  4. Obtain certifications for special processes
  5. Address all non-conformances before approval
  6. Maintain FAI records per retention requirements

Integration Points

  • Connects with GD&T Drawing for requirements
  • Feeds into Design Review for verification evidence
  • Supports Process Planning for capability verification
  • Integrates with Quality systems for record keeping